(a) A project which provides for the construction, reconstruction, acquisition or installation of a physical public betterment or improvement which would be classified as a capital asset under generally accepted accounting principles for municipalities or any preliminary studies and surveys relative thereto or any underwriting or other costs incurred in connection with the financing thereof.
(b) The acquisition of property of a permanent nature including wharf property.
(c) The acquisition of any furnishings, machinery, apparatus or equipment for any public betterment or improvement when such betterment or improvement is first constructed or acquired.
(d) Any public betterment involving either a physical improvement or the acquisition of real property for a physical improvement consisting in, including or affecting:
(1) Streets and parks;
(2) Bridges and tunnels;
(3) Receiving basins, inlets and sewers, including intercepting sewers, plants or structures for the treatment, disposal or filtration of sewage, including grit chambers, sewer tunnels and all necessary accessories thereof;
(4) The fencing of vacant lots and the filling of sunken lots.
(e) Any other project allowed to be financed by the local finance law, with the approval of the mayor and the comptroller.
(f) Any combination of the above.
2. The term "pending" shall mean not yet completed.
3. The term "standards" for each category of capital projects to which they apply shall include: maximum gross and net areas allowed; types of programs which may be operated in the facility; performance requirements for environmental systems; allowable materials and finishes; maximum areas allowed for different functions and activities; approximate cost limits per square foot of construction; and such other items designated by the mayor or by resolution of the council.
4. The term "scope of project" or "proposed scope of project" shall mean a description of a capital project included in the capital budget that contains specific guidelines for the design and implementation of such project consistent with the standards for the appropriate category of capital projects and includes each of the following items of information which are relevant to the capital project involved:
(a) Purposes and public to be served;
(b) Programs to be conducted in the facility;
(c) Gross and net amounts of space and bulk for any building or structure and for areas for different functions and activities;
(d) Identification of required architectural, engineering or other consultants and estimated fees for such consultants;
(e) Estimated completion dates for scope, design and construction;
(f) Total estimated project costs, including costs for site acquisition, preparation and tenant relocation, design, construction and equipment;
(g) Estimated expenditures for the project for each fiscal year until its completion;
(h) Estimated annual costs to operate programs within the facility when fully staffed and to maintain the facility; and,
(i) Such other information as shall be required by the mayor or by resolution of the council.
5. The term "cost" shall include the contract liabilities and expenditure incurred for work in carrying out the physical improvement and interest thereon, and the compensation to be made to the owner of any real property acquired for the improvement as determined by a court or by agreement, and interest thereon.
6. The term "expenses" shall mean any expenses incurred in relation to an assessable improvement exclusive of cost and of damages assessed by the board of assessors.
7. The term "street," as used in this chapter, shall include street, avenue, road, alley, lane, highway, boulevard, concourse, parkway, driveway, culvert, sidewalk, crosswalk, boardwalk, and viaduct, and every class of public road, square and place, except marginal streets.
8. The term "real property" shall include all lands and improvements, lands under water, water front property, the water of any lake, pond or stream, all easements and hereditaments, corporeal or incorporeal, and every estate, interest and right, legal or equitable, in lands or water, and right, interest, privilege, easement and franchise relating to the same, including terms for years and liens by way judgment, mortgage or otherwise.
Section 211. Capital budget borough allocations.
a. Borough allocation. Five percent of the appropriations, funded by debt supported by city tax levy funds and state and federal funds over which the city has substantial discretion, proposed in the executive capital budget for the ensuing fiscal year, except any lump sum appropriation for school construction or rapid transit proposed to be made to public authorities established pursuant to the provisions of state law, shall be allocated among the boroughs by a formula based on an equal weighting of factors relating to population and geographic area, and shall be known as the capital budget borough allocation. Such formula shall be established by local law, but in any fiscal year for which no such local law is effective such amount shall be allocated among the boroughs on the basis of the average of (i) each borough's share of the total population of the city, and (ii) each borough's share of the total land area of the city.
b. Preliminary borough allocations; initial borough president notification. Concomitantly with the submission of the preliminary capital budget and preliminary certificate, the mayor shall inform each borough president of the portion of the executive capital budget for the ensuing fiscal year and of the executive capital budgets for each of the three succeeding years that, pursuant to the formula required by subdivision a of this section, would be allocated to each borough if the amount of the appropriations proposed in the executive capital budget for each of such fiscal years were the same as the maximum amounts of appropriations for such years which the mayor anticipates to be certified in the preliminary certificate issued in accordance with section two hundred thirty-five. The amount of such portion shall be known as the preliminary capital budget borough allocation.
c. Borough president proposals.
1. Each borough president, during the consultations required by section two hundred forty-four, shall submit to the mayor, in such form as the mayor shall prescribe, proposed capital appropriations in an amount not exceeding that borough's allocation of the capital budget borough allocation as certified by the mayor to the borough presidents during such consultations. The timing of such certification shall allow sufficient time for such consultations and for meeting the deadlines established by section two hundred forty-nine. Each such proposed appropriation shall be accompanied by the following information:
(a) for each such proposed appropriation for construction of a capital project, the estimated annual cost to operate and maintain the facility to be constructed pursuant to such appropriation when construction is completed. Such estimates shall be prepared in accordance with the standards established for this purpose pursuant to section two hundred twenty-one of this chapter and shall be certified by the director of the office of management and budget. In the event that a borough president and the director of management and budget do not agree on such estimate for a particular project, such director and the director of the independent budget office shall jointly certify an estimate for such purpose;
(b) for each such proposed appropriation for the planning and design of a capital project, (i) the estimated cost of the construction of the project, and (ii) the fiscal year in which the borough president intends to propose an appropriation for the construction of the project, if no technical problems regarding the viability of the project are identified during planning, site selection or design;
(c) the total of all appropriations which will be necessary during the three ensuing fiscal years to provide for the construction of projects for which planning and design appropriations are being proposed.
2. If a borough president proposes an appropriation for the construction of a capital project, the appropriation must provide for the total amount estimated to be necessary for the completion of the project. If such a proposed appropriation for the construction of a capital project is for an amount which is less than the amount that the office of management and budget estimates to be necessary for the completion of the project, the borough's capital budget borough allocation in any future year in which additional appropriations are necessary for the completion of the project shall be reduced by the amount of such additional appropriations.
3. If the total appropriations necessary, during any of the ensuing three fiscal years, to provide for the construction of (i) projects for which the borough president is proposing appropriations for planning and design, and (ii) projects for which appropriations were previously made for planning and design on the recommendation of the borough president, is greater than the capital budget borough allocation anticipated to be available during such years based on the certificate issued pursuant to paragraph sixteen of section two hundred fifty of this charter, then the borough president shall submit for inclusion in the executive budget a list of the projects requiring construction appropriations during such year, in priority order.
4. If the estimated annual cost to operate and maintain the capital projects being proposed for construction by a borough president is greater than the amounts dedicated to such expense budget purposes from the expense budget borough allocation and the capital budget borough allocation expense budget contingency projected to be available to the borough president in one or more ensuing fiscal years then such proposed appropriations may only be included by a borough president in the capital budget with the concurrence of the mayor.
d. The mayor shall include the proposed appropriations submitted by the borough presidents in accordance with subdivision c of this section in the executive capital budget provided however, that the mayor may also include such comments and recommendations relating to such proposals as the mayor deems appropriate.
Section 212. Format of departmental estimates for capital projects, preliminary capital budget and executive capital budget.
The departmental estimates for capital projects and the executive capital budget shall consist of a detailed estimate of all capital projects pending or which the agency head, for departmental estimates, or the mayor, for the executive budget, believes should be undertaken within the ensuing fiscal year and the three succeeding fiscal years. Each agency head, for departmental estimates, and the mayor, for the executive budget, shall submit a written response to each of the capital budget priorities included in the community board's statement of budget priorities submitted in accordance with section two hundred thirty. Such responses shall include the response of the agency head and the mayor, as appropriate, regarding the disposition of each such priority and meaningful explanations of any disapprovals contained in such estimates or budget.
Section 213. Preliminary capital budget.
The preliminary capital budget shall consist of: (1) a financial plan, consistent with section two hundred fifty-eight, covering estimates of capital expenditures for the four ensuing fiscal years, (2) departmental estimates for capital projects as provided in section two hundred twelve together with the cash flow requirements and proposed sources of funding for each project included in such estimates, (3) a capital program status report which sets forth the appropriations for each project included in the capital budget for the current fiscal year together with the expenditures to date, and (4) a summary description of the purpose of each capital project and the needs it will fulfill, the schedule for beginning and constructing the project, its period of probable usefulness and an appropriate maintenance schedule.
Section 214. Executive capital budget.
a. The executive capital budget shall set forth separately each capital project, including the capital projects proposed by the borough presidents in accordance with section two hundred eleven, and shall include:
(1) A brief description and the location of each project; the total estimated cost of the project; the appropriations which have been previously adopted for this project; the amount of appropriations recommended to be adopted for the ensuing fiscal year, the aggregate amount of which shall not exceed the amount in the mayor's certificate; the amount of appropriations required thereafter to complete the project; the sources of funds for the project including state, federal, private and other funds; the period of probable usefulness; the estimated additional annual maintenance and operation costs; any terms and conditions of the project; and the estimated dates of completion of final scope, final design and final construction;
(2) A listing of all pending projects; and any recommendations that any pending projects be modified, rescinded or postponed accompanied by a statement of the budgetary impact of any such action; and
(3) A listing of proposed capital projects by community district and by borough and an identification of those projects which were included in the statement of capital priorities submitted by each community board and borough board.
b. The executive capital program shall set forth for both program categories and individual projects:
(1) A statement for each of the three succeeding fiscal years of the total dollar amounts necessary to complete projects initiated in prior years and projects proposed in the executive budget, the amounts necessary for projects proposed to be initiated in future years and the amounts necessary for amendments and contingencies; and
(2) A statement of the likely impact on the expense budget of staffing, maintaining and operating the capital projects included in or contemplated by the capital program.
Section 215. Ten-year capital strategy.
a. The ten-year capital strategy shall be issued by the mayor pursuant to section two hundred forty-eight after (i) submission of a preliminary strategy by the department of city planning and the office of management and budget pursuant to section two hundred twenty-eight, and (ii) submission of a report on the preliminary strategy by the city planning commission following a public hearing, pursuant to section two hundred thirty-four.
b. Contents of ten-year capital strategy. Each ten-year capital strategy shall include:
(1) a narrative describing the strategy for the development of the city's capital facilities for the ensuing ten fiscal years; the factors underlying such strategy including goals, policies, constraints and assumptions and the criteria for assessment of capital needs; the anticipated sources of financing for such strategy; and the implications of the strategy, including possible economic, social and environmental effects;
(2) tables presenting the capital commitments estimated to be made during each of the ensuing ten fiscal years, by program category and agency. Where relevant the anticipated sources of financing for particular categories and projects shall be specified; and
(3) a map or maps which illustrate major components of the strategy as relevant.
c. In the preparation of the preliminary ten-year capital strategy, the department of city planning and office of management and budget shall consider (i) the strategic policy statements of the mayor and the borough presidents pursuant to section seventeen, (ii) relevant citywide, borough and community plans adopted pursuant to section one hundred ninety seven-a, and (iii) the reports pursuant to section two hundred fifty-seven comparing the most recent ten-year capital strategy with the capital budgets and programs adopted for the current and previous fiscal years.
Section 216. Amendment.
a. Upon receipt of a recommendation in writing from the mayor or a borough president, in manner specified herein, the council may amend the capital budget or capital program in the same manner as the adoption of the capital budget and capital program including the right to approve the proposed amendment as submitted or to increase or decrease the amounts of funds proposed to be appropriated thereby, but only if funds are available within the capital budget and the applicable program category of the capital program; provided, however, that (i) the mayor may only recommend such an amendment relating to an appropriation included in the capital budget pursuant to section two hundred eleven with the concurrence of the relevant borough president; and (ii) the borough president may only make such a recommendation with regard to such an appropriation if it provides for an offsetting reduction in another appropriation included in the capital budget pursuant to section two hundred eleven on the recommendation of such borough president and it is concurred in by the mayor.
b. Upon the adoption of any such amendment by the council, it shall be certified by the mayor, the public advocate and the city clerk and the capital budget shall be amended accordingly.
c. Not later than five days after such certification such amendment shall be filed in the office of the comptroller and shall be published forthwith in the City Record.
Section 217. Restrictions on capital projects.
a. No obligations of the city shall be issued or authorized for or on account of any capital project not included in a capital budget, or for which funds have not been reserved in an appropriate program category of the capital program for any year of such program in which it is projected that funds will be expended for the completion of the project, or in excess of the maximum amount of obligations which may be issued on account of such project as fixed in such capital budget; and no amount may be expended on account of any capital project in excess of the amount appropriated for such purposes in a capital budget, except that the amount appropriated for such purposes may be increased by the mayor by not more than fifteen per centum thereof in order to meet any costs required to advance such project. Notice of any such increase shall be provided to the council together with a statement of identifiable funds available for payment of the increase.
b. Funds included in the capital budget for a capital project that are not obligated or committed during the fiscal year in which appropriated shall not be obligated or committed in the subsequent fiscal year unless reappropriated in a subsequent capital budget or an amendment thereto. A capital project included in a capital budget that is not initiated by the expenditure of funds within two years after its inclusion in the budget shall be eliminated from the budget.
c. The city may issue capital debt only to finance capital projects as defined in section two hundred ten. The capital budget may not include expense items that are properly includable only in the expense budget, as determined in accordance with the accounting principles set forth in the state comptroller's uniform system of accounts for municipalities, as the same may be modified by the state comptroller, in consultation with the city comptroller, for application to the city.
d. No capital project shall be included in the proposed executive capital budget or otherwise adopted as part of the capital budget or as an amendment thereto unless sufficient funds are available within the appropriate general program category of the capital program for any year of such program in which it is projected that additional appropriations will be necessary for the completion of the project.
b. To the maximum extent feasible, final approval of a site for a capital project shall occur prior to or simultaneously with the approval of the scope of the project pursuant to this chapter.
c. During the review required by subdivision a, the community board and borough president shall also review, and may comment on, the scope of the project.
Section 219. Project initiation; commitment plan.
a. The inclusion of a capital project in the capital budget as adopted or amended shall constitute a direction and order to the agency to proceed with the preparation of a scope of project pursuant to this chapter unless sufficient planning funds for such purpose have not been appropriated in the capital budget. The head of the agency shall notify the comptroller of the amount of appropriated planning funds to be encumbered for such purpose.
b. The approval of a scope of project for a capital project pursuant to this chapter, including the amount of obligations necessary to finance the design and construction of the project, shall constitute a direction and order to the agency to design the project, unless sufficient funds for such purpose have not been appropriated in the capital budget or are otherwise not available within the appropriate program category of the capital program. Such approval shall constitute notification to the comptroller of the comptroller's authorization to expend appropriated design funds.
c. The approval of the final design for a capital project pursuant to this chapter shall constitute a direction and order to the agency responsible for construction to prepare bid and award documents and to proceed to bid, unless sufficient funds for such purpose have not been appropriated in the capital budget or are otherwise not available within each year of the capital program in which it is projected that funds will be expended for the completion of the project. Such approval shall constitute notification to the comptroller of the comptroller's authorization to expend appropriated construction funds.
d. The mayor shall require each agency to prepare and submit periodic reports in regard to the progress of its capital projects, including schedules and clear explanations of any delays for particular projects and summary information on each agency's record on such matters. Such reports shall be published at least three times each year: no later than 120 days after the adoption of the capital budget; no later than 30 days after submission of the preliminary capital budget; and no later than 30 days after submission of the executive capital budget. Copies of such reports shall be transmitted by the mayor to the council, the city planning commission, the community boards, the borough boards and borough presidents, and posted online on the website of the office of management and budget in a machine-readable format. Such reports shall include, for each project, the dates set in the adopted capital budget for the completion of scope, design, and construction and any changes in such dates.
1. The report issued with the executive budget shall include, for each new capital project being proposed in the executive budget, a description of the project including, to the extent practicable, the information required to be included in a scope of project by paragraph four of section two hundred ten.
2. The report issued following the adoption of the budget shall include, for each capital project added to the budget, a description of the project including, to the extent practicable, the information required to be included in a scope of project by paragraph four of section two hundred ten.
3. The report issued following the adoption of the budget shall include, for each capital project for which a substantial change was made, a revised description of the project including, to the extent practicable, the information required to be included in a scope of project by paragraph four of section two hundred ten.
e. Any capital project which results in the acquisition or construction of a capital asset which will be subject to the requirements of section eleven hundred ten-a shall contain a provision requiring a comprehensive manual setting forth the useful life of the asset and explaining the activities necessary to maintain the asset throughout such useful life.
f. The mayor may issue directives and adopt rules and regulations in regard to the execution of capital projects, consistent with the requirements of subdivisions a, b, c and d of this section, which shall be binding upon all agencies.
(Am. L.L. 2020/037, 3/13/2020)
Section 220. Improvements payable other than by city.
Any owner of real property or any other person interested may apply to the council to authorize an improvement referred to in paragraph d of subdivision one of section two hundred ten hereof, not included in the capital budget. The council may authorize such improvement to be made by the city or by such owner or other person interested upon compliance with the following conditions:
1. Such owner or group or other persons interested shall enter into an agreement with the city, whereby they will either authorize the city, or themselves agree, to perform such work in accordance with such plans and specifications approved by the agencies having jurisdiction thereover and under their supervision.
2. All of such work shall be done for the account of or at the sole cost and expense of the person or persons applying for permission to do the same, who shall furnish to the city such security and in such amount as may be required to secure the payment of such cost and expense or the proper performance of the said work in the time and in the manner agreed upon, and shall further secure the city, in the latter case, against latent defects in such work for a period of two years.
4. Any agreement providing for the performance of such work and the furnishing of such security, shall be first approved by the council before the same shall become effective.
Section 221. Standards for capital projects.
The mayor shall prepare general standards and cost limits for categories of capital projects and standards for the preparation of the scope of project for capital projects of various types. Such standards and limits shall be submitted by the mayor to the council for review. The proposed standards shall become effective thirty days after they have been filed with the council unless within that time the council modifies or disapproves them or part of them, after conducting a public hearing. Any modification by the council shall be subject to disapproval by the mayor in accordance with section thirty-eight and any such disapproval shall be subject to override by the council in accordance with such section.
Section 222. Scope of project.
a. Each agency, with respect to a capital project under its jurisdiction included in a capital budget, shall prepare a proposed scope of project within appropriated planning funds. In preparing the proposed scope of project, the agency shall consult with the community board for the community district in which the capital project is to be located. The proposed scope of project, or, in the case of a delay, an explanation for such delay along with a revised schedule, shall be submitted to the mayor and to the respective council committee, borough president and community board by the date specified in the adopted capital budget in which the capital project is included. Such proposed scope shall identify all substantial differences between the guidelines for the capital project as contained in such scope and the description of the capital project contained in the report issued pursuant to subdivision d of section two hundred nineteen at the time such project was proposed in the executive budget or following the budget adoption in which such project was added to the capital budget.
b. Not later than sixty days after receipt of the proposed scope of project from an agency pursuant to subdivision a of this section, the mayor shall approve, modify, or disapprove the proposed scope of project and notify the agency, and the respective council committee, borough president and community board. In the case of a scope approved by the mayor with modifications, such notification shall include a copy of the scope as approved.
c. During the review of the selection of a site of a capital project pursuant to the uniform land use review procedure established by section one hundred ninety-seven-c, the community board and borough president shall also review, and may comment on, the scope of the project.
d. No scope of project shall be approved by the mayor unless (1) it contains the information required by paragraph four of section two hundred ten and it conforms to the applicable standards for the type of project adopted pursuant to this chapter, and (2) funds are available within the appropriate program category of the capital program that can be reserved for each fiscal year required to complete the project.
Section 223. Design of capital project.
The proposed design and final design for a capital project shall be made available for review to the respective council committee, borough president and the community board for the community district in which the project is to be located. The mayor or his representative shall review the final design to determine its conformance with the approved scope of project pursuant to this chapter.
Section 224. Works of art.
a. For purposes of this section:
b. Works of art shall be provided for each capital project which involves the construction or the substantial reconstruction of a city-owned public building or structure the intended use of which requires that it be accessible to the public generally or to members of the public participating in, requiring or receiving programs, services or benefits provided thereat.
c. An amount not less than one percent of the first fifty million dollars and one-half of one percent of any amount in excess of fifty million dollars of capital funds appropriated by the city for each such capital project, other than funds appropriated for the acquisition of real property, shall be allocated for works of art; provided, however, that this section shall in no case require, but shall not prohibit, the expenditure of more than nine hundred thousand dollars for works of art for any capital project nor more than the sum of four million dollars for all works of art in any fiscal year. The mayor may exempt a capital project from the provisions of this section if in the mayor's sole judgment the inclusion of works of art as provided hereby would be inappropriate.
d. 1. The department of cultural affairs shall engage in outreach and education efforts regarding the opportunity to submit works of art for consideration for inclusion in capital projects as provided for by this section. Such outreach and education efforts shall include but not be limited to information sessions in each borough that shall be open to the public and the development of written materials that describe the submission and selection process for works of art. The department shall make such written materials available in a manner deemed appropriate by the department, including but not limited to making such materials available to arts and cultural organizations, community-based organizations, and colleges and universities. Such written materials shall be made available in English and in the six languages most commonly spoken by limited English proficient individuals in the city as determined by the department of city planning.
2. Reasonable advance notification of the intention to include works of art in a project shall be provided to the appropriate council member, borough president and chairperson of the community board of the community district in which the project is located. Reasonable advance notification of the intention to include works of art in a project shall also be posted on the website of the department of cultural affairs. Following notification of the intention to include works of art in any project, the department of cultural affairs shall hold or present at a public meeting, such as a meeting of the community board of the community district in which the project is located, on such works of art prior to such inclusion. A notice of such public meeting shall be posted on the website of the department of cultural affairs not less than fourteen days prior to any such meeting. All such works of art shall be subject to the approval of the art commission pursuant to section eight hundred fifty-four of this charter.
e. The mayor shall adopt rules and regulations to implement the provisions of this section.
f. The department of cultural affairs shall post on the department’s website information about works of art that were included in a capital project pursuant to this section after the effective date of the local law that added this subdivision.
1. Such information shall include but not be limited to the name of the work of art; name of the artist; capital project completion date; medium and dimensions of the work of art; location of the work of art, including council district and borough; sponsor agency; and design agency.
2. The department shall post on the department’s website aggregated demographic information about the artists whose works of art are subject to the provisions of this subdivision, to the extent such demographic information is provided to the department.
g. There shall be an advisory panel to recommend eligible works of art to be included in a capital project pursuant to this section. The commissioner of cultural affairs or his or her designee shall serve as chairperson of such panel and shall ensure that such panel includes members who are knowledgeable about public art, knowledgeable about the project, and knowledgeable about the community in which the project will be located. The panel shall further include but not be limited to at least one representative of the president of the borough in which the project will be located, at least one representative of the council member in whose district the project will be located, and at least one representative of the community board for the community district in which the project will be located, provided, however, that such representatives shall be non-voting ex officio members.
*Editor's note: this Section 224.1 was substantially amended by L.L. 2016/031 and L.L. 2016/032, both enacted 3/28/2016, to appear as set out below. Section 4 of L.L. 2016/032 provides the following regarding its effectiveness and applicability: "This local law takes effect immediately, except that this local law shall apply only to capital projects which are added to the capital plan on or after July 1, 2017. All other capital projects shall comply with section 224.1 of such charter, as in effect before the effective date of this local law, subject to the provisions of section four of local law 86 for the year 2005." For the convenience of the code user, the version of this Section 224.1 as it existed immediately prior to the effectiveness of L.L. 2016/032** may be viewed in its entirety by clicking here .
a. As used in this section the following terms shall have the following meanings:
b. (1) Except as provided in paragraphs (3) of this subdivision, each capital project with an estimated construction cost of $2,000,000 or more involving (i) the construction of a new building, (ii) an addition to an existing building, or (iii) the substantial reconstruction of an existing building shall be designed and constructed to comply with green building standards not less stringent than the standards prescribed for buildings designed in accordance with the LEED green building rating system to achieve a LEED gold or higher rating, or, with respect to buildings classified in groups F or H, to achieve a LEED certified or higher rating, or with respect to buildings classified in occupancy group R, to comply with the version of the New York city overlay of the Enterprise green communities criteria in effect as of the effective date of the local law adding paragraph (3) of this subdivision, or the version of such criteria designated by the department of housing preservation and development by rule; provided that capital projects with an estimated construction cost of less than $10,000,000 and that involve only an addition to or substantial reconstruction of an existing building classified in occupancy groups F or H are exempted from complying with this subdivision; and further provided that capital projects with an estimated construction cost of $10,000,000 or more involving an addition to or substantial reconstruction of an existing building classified in occupancy groups F or H may be designed and constructed as low energy intensity buildings, as defined in subdivision l of this section, in lieu of complying with this subdivision. If the mayor elects to utilize green building standards other than the LEED green building rating system, the mayor shall publish findings demonstrating that such other green building standards are not less stringent than the LEED standards described above for achievement of a LEED gold or, if applicable, a LEED certified rating. The green building standards utilized by the city in accordance with this section shall be reviewed and updated, as necessary, by the mayor no less often that once every three years.
(2) In addition, if the estimated construction cost of a capital project required to comply with green building standards in accordance with paragraph (1) of this subdivision is $12,000,000 or more, such project shall be designed and constructed to reduce energy cost as follows; provided that this paragraph shall not apply to capital projects involving city-owned buildings or buildings classified in occupancy groups E or R:
(i) Capital projects with an estimated construction cost of $12,000,000 or more but less than $30,000,000 shall be designed and constructed to reduce energy cost by a minimum of 20 percent, as determined by the methodology prescribed in LEED energy and atmosphere: optimize energy performance credit or the New York state energy conservation code, whichever is more stringent. In addition to such 20 percent reduction in energy cost, the design agency shall make investments in energy efficiency that reduce energy cost by an additional five percent if it finds that the payback on such investment through savings in energy cost would not exceed seven years.
(ii) Capital projects with an estimated construction cost of $30,000,000 or more shall be designed and constructed to reduce energy cost by a minimum of 25 percent, as determined by the methodology prescribed in LEED energy and atmosphere: optimize energy performance credit or the New York state energy conservation code, whichever is more stringent. In addition to such 25 percent reduction in energy cost, the design agency shall make investments in energy efficiency that reduce energy cost by an additional five percent if it finds that the payback on such investment through savings in energy cost would not exceed seven years.
(3) For capital projects required to comply with paragraph (1) of this subdivision which are buildings classified in occupancy groups E, I-2 or in any occupancy group that, before the enactment of the local law adding this paragraph, was not required to comply with paragraph (1) of this subdivision, the mayor or an office or agency designated by the mayor may, in conjunction with the New York city economic development corporation, the New York city school construction authority and any other relevant offices or agencies, establish alternative design and construction standards. Such alternative standards may be as stringent or more stringent than the standards described by paragraph (1) of this subdivision. For buildings that are not classified in occupancy group E, such alternative standards may be less stringent than the standards described by paragraph (1) of this subdivision if the mayor or such designated office or agency determines that compliance with the standards described by such paragraph would be impracticable or unduly burdensome for a particular occupancy group; provided that such alternative standards may be less stringent than the standards described by such paragraph only to the minimum extent necessary and, except in the case of alternative standards prescribed for buildings classified in occupancy group R, shall be not less stringent than standards prescribed for buildings designed to achieve a LEED certified rating under version 4 of the LEED green building rating system. For buildings that are classified in occupancy group E, such alternative standards may be the New York city green schools guide in effect as of the effective date of the local law adding this paragraph, or the version of such guide designated by rule by the mayor or such designated office or agency; provided that such alternative standards are not less stringent than standards prescribed for buildings designed to achieve a LEED certified rating under version 4 of the LEED green building rating system. If the mayor or such designated office or agency establishes alternative standards under this paragraph, the mayor or such designated office or agency shall:
(i) Within 60 days after adopting such alternative standards, submit to the council and make publicly available online a report that, at a minimum:
(A) Describes such standards and the occupancy groups to which they will apply;
(B) Identifies any provisions in such standards that are less stringent than the standards described in paragraph (1) of this subdivision and, for each such provision, sets forth the reasons why compliance with the standards described in such paragraph would be impracticable or unduly burdensome for buildings classified in such occupancy groups;
(C) Except in the case of alternative standards prescribed for buildings classified in occupancy group R, describes how such alternative standards are not less stringent than the standards prescribed for buildings designed to achieve a LEED certified rating under version 4 of the LEED green building rating system; and
(ii) If such alternative standards are less stringent than the standards described in paragraph (1) of this subdivision, in every third fiscal year thereafter, submit to the council and make publicly available online a report that, at a minimum, states whether the mayor or such designated office or agency has determined that such less stringent standards continue to be necessary and, if so, a description of the reasons therefor and whether such standards can reasonably be made more stringent.
c. Capital projects, other than those required to comply with green building standards in accordance with subdivision b of this section, shall be subject to the following:
(1) Each capital project that includes the installation or replacement of a boiler at an estimated construction cost for such installation or replacement of $2,000,000 or more, or that involves the installation or replacement of lighting systems in a building at an estimated construction cost for such installation or replacement of $1,000,000 or more, shall be designed and constructed to reduce energy cost by a minimum of ten percent, as determined by the methodology prescribed in LEED energy and atmosphere: optimize energy performance credit or the New York state energy conservation code, whichever is more stringent; provided that compliance with this paragraph shall not be required for capital projects that would be subject to this paragraph solely because such project involves replacement of a boiler, unless the cost of such project equals or exceeds 50 percent of the cost of replacing the heating distribution system of such building.
(2) Each capital project, other than a project required to comply with paragraph (1) of this subdivision, that involves the installation or replacement of HVAC systems at an estimated construction cost for such installation or replacement of $2,000,000 or more, shall be designed and constructed to reduce energy cost by a minimum of five percent as determined by the methodology prescribed in LEED energy and atmosphere: optimize energy performance credit or the New York state energy conservation code, whichever is more stringent.
d. In addition to complying with any other applicable subdivision in this section, each capital project involving the installation or replacement of plumbing systems that includes the installation or replacement of plumbing fixtures at an estimated construction cost for such installation or replacement of plumbing systems of $500,000 or more shall be designed and constructed to reduce potable water consumption in the aggregate by a minimum of 30 percent, as determined by a methodology not less stringent than that prescribed in LEED water efficiency: indoor water use reduction credit; provided, however, that such percentage shall be reduced to a minimum of 20 percent if the department of buildings rejects an application for the use of waterless urinals for the project.
e. This section shall not apply to capital projects that only involve buildings classified in occupancy groups A-5 or U.
f. The mayor may exempt from each provision of this section capital projects accounting for up to 20 percent of the capital dollars in each fiscal year subject to such provision if in such mayor's sole judgment such exemption is necessary in the public interest. At the conclusion of each fiscal year the mayor shall report to the council the exemptions granted pursuant to this section.
g. This section shall not apply to capital projects of entities that are not city agencies unless 50 percent or more of the estimated cost of such project is to be paid for out of the city treasury. This exemption shall not apply to any capital project that receives $10,000,000 or more out of the city treasury.
h. This section shall not apply to capital projects that have received capital dollars from the city treasury before January 1, 2007.
i. The mayor shall promulgate rules to carry out the provisions of this section.
j. The costs listed in subdivisions b, c, d and g of this section are denominated in January 2007 dollars and shall be indexed to inflation annually.
k. Capital projects that are subject to paragraph (1) of subdivision b of this section that utilize a version of the LEED green building rating system for which the U.S. Green Building Council will accept applications for certification, shall apply to the U.S. Green Building Council for certification that such projects have achieved a gold or higher rating under the LEED green building rating system. The mayor or an office or agency designated by the mayor shall by rule establish an alternative certification process for capital projects that are complying with alternative standards promulgated by the mayor or such designated office or agency under paragraph (3) of subdivision b of this section.
l. (1) As used in this subdivision:
(2) (i) Each capital project that involves the construction of a new city-owned building and each capital project that involves an addition to an existing city-owned building or the substantial reconstruction of an existing city-owned building, where such substantial reconstruction involves substantial work on the building envelope, shall be designed and constructed as a low energy intensity building.
(ii) For each capital project subject to subparagraph (i) of this paragraph the design agency shall consider the feasibility of designing and constructing such project as an onsite energy generating building.
(iii) For each capital project subject to subparagraph (i) of this paragraph with an estimated height of no more than three stories above grade, the design agency shall consider the feasibility of designing and constructing such project as a net zero energy building.
(iv) For each capital project subject to subparagraph (i) of this paragraph the design agency shall consider the feasibility of designing and constructing such project to incorporate green infrastructure.
(v) This paragraph shall apply only to capital projects which are added to the capital plan on or after July 1, 2017.
(3) The mayor, or an office or agency designated by the mayor, may establish an alternative low energy intensity target for buildings designed and constructed for a particular use, or for additions to, or substantial reconstructions of, existing buildings. Such alternative target may be equivalent to or more stringent than the low energy intensity target or, if the mayor or such designated office or agency determines that compliance with subparagraph (i) of paragraph (2) of this subdivision would be impracticable or unduly burdensome for such buildings or such work using the low energy intensity target, less stringent than such target. Where the mayor or such designated office or agency adopts such an alternative target, the mayor or such designated office or agency shall, no later than 60 days after such adoption, submit to the council and make publicly available online a report describing such alternative target and the types of buildings or work to which it will apply. If such alternative target is less stringent than the corresponding low energy intensity target, such report shall set forth the reasons that compliance with subparagraph (i) of paragraph (2) of this subdivision using such low energy intensity target would be impracticable or unduly burdensome for such types of buildings or work and, in each fiscal year thereafter, the mayor or such designated office or agency shall submit to the council and make publicly available online a report stating whether the mayor or such designated office or agency has determined that such alternative targets continue to be necessary and, if so, a description of the reasons therefor and whether such targets can reasonably be made more stringent.
(4) No later than January 1, 2017, the mayor shall submit to the speaker of the council and make publicly available online a plan for ensuring that by 2030 capital projects subject to paragraph (2) of this subdivision will be designed and constructed so that new buildings have a source energy use intensity no greater than 38 kBTU/yr per square foot of floor area and that additions to, or substantial reconstructions of, existing buildings have a source energy use intensity of no greater than 42 kBTU/yr per square foot of floor area. Such plan shall include a list of policies, programs and actions that the city will seek to undertake to achieve such targets.
(5) In 2019 and every third year thereafter, the mayor shall, by June 30 of such year, submit to the speaker of the council and make publicly available online a report containing, at a minimum, recommended practices for designing and constructing low energy intensity buildings.
m. By no later than December 1 of each year, the mayor shall submit to the speaker of the council a report, in accordance with the procedure and format established by the department of design and construction, containing, at a minimum, the following information:
(1) for each capital project subject to this section completed during the preceding fiscal year:
(i) a brief description of such project, including the total cost of the project;
(ii) the street address of such project and the community district and council district in which such project is located;
(iii) the estimated level of LEED certification such project has achieved as determined by the city agency that designed such project in accordance with the LEED green building rating system or, if applicable, the level achieved, as certified by the U.S. Green Building Council;
(iv) additional costs attributed to complying with the LEED green building rating system or any other green building standard;
(v) a statement as to whether such project has been designed and constructed as a low energy intensity building, onsite energy generating building or a net zero energy building and, for each project designed and constructed as a low energy intensity building, the low energy intensity target for such building or if the mayor, or an office or agency designated by the mayor, has adopted an alternative low energy intensity target pursuant to paragraph (3) of this subdivision, such alternative target;
(vi) if such capital project was not designed and constructed as an onsite energy generating building, a description of the reasons therefor, a statement as to whether such building has been designed and constructed to produce any energy onsite from renewable energy sources and, if so, the amount of such onsite energy production expressed as a percentage of the building's total energy needs;
(vii) additional costs attributable to complying with the low energy intensity building requirements, the onsite energy generating requirements and the net zero energy building requirements of paragraph (2) of subdivision 1 of this section; and
(viii) an assessment of the health, environmental and energy-related benefits achieved in comparison with a base-case code compliant project, including projected energy savings and reductions in peak load, reductions in emissions and potable water use;
(2) for each capital project subject to paragraph (2) of subdivision l that was commissioned before the preceding fiscal year and that is not a low energy intensity building, a summary of remedial actions taken and to be taken and the anticipated or actual start and completion dates of such actions;
(3) a summary of agency findings related to additional investment in energy efficiency pursuant to subparagraphs (i) and (ii) of paragraph 2 of subdivision b of this section, including any additional investment in energy efficiency considered and the estimated payback time for such investment through savings in energy cost; and
(4) the total value of capital allocations in the preceding calendar year to projects exempted from the requirements of this section by the mayor pursuant to subdivision f of this section, and a list and brief description of each such project, including but not limited to square footage, project cost and the reason for such exemption, disaggregated by city agency.
Section 224.2. Required energy conservation projects in city buildings.
a. Definitions. For the purposes of this section, the terms "base building systems", "city building", "energy audit", "energy efficiency report", and "simple payback" shall have the same meanings as defined in section 28-308.1 of the administrative code.
b. No later than one year after the submission, in accordance with article three hundred eight of chapter three of title twenty-eight of the administrative code, of an energy efficiency report for a city building, reasonable capital improvements to the building's base building systems that are recommended in the building's energy audit shall be completed, including, at a minimum, all those improvements of the base building systems having a simple payback of not more than seven years or capital improvements that, when combined, would equal or exceed the overall reduction in energy consumption of such recommended capital improvements having a simple payback of not more than seven years.
c. The mayor shall promulgate rules as may be necessary to carry out the provisions of this section.
Section 224.3. Induction loop systems.
a. As used in this section, the following terms have the following meanings:
b. Each capital project with an estimated baseline construction cost of $950,000 or more involving the construction or reconstruction of one or more assembly areas shall be designed and constructed to include in at least one assembly area the installation of an induction loop assistive listening system that complies with section N102 of appendix N of the New York city building code, or an alternative assistive listening system that complies with appendix N of the New York city building code that has been determined by the mayor in accordance with subdivision i of this section to be significantly more effective for the hard of hearing than an induction loop system. Each security, information, or reception desk used for the checking-in or screening of persons attending a meeting or event held in a looped assembly area shall be equipped with microloops. This section shall not apply to a capital project involving the reconstruction of an assembly area if the estimated cost of installing an induction loop system or alternative system exceeds 5% of the baseline construction cost of the project.
c. Directional signage that includes guidance to an assistive listening assembly area, including raised graphics and letters with Braille descriptors, must be provided in accordance with section 1110.2 of the New York city building code, and other signage indicating any special accessibility features must be provided in accordance with section 1110.3 of such code.
d. The entrance to any building containing an assistive listening assembly area and any security, information, or reception area used for the checking-in or screening of persons attending a meeting or event held in such assembly area shall display the international symbol of access for hearing loss pursuant to figure 703.6.3.3 of ICC A117.1 - 2009 and a “T” in the lower right-hand corner of such symbol indicating the availability of an induction loop system or a symbol indicating an alternative system if applicable.
e. No later than July 1, 2018, the mayor or an office or agency designated by the mayor shall post on its website the locations of facilities owned or operated by the city at which an assistive listening system such as an induction loop, infrared, FM, or other type of system, is permanently available or in the process of being installed, as well as which type of assistive listening system is permanently available or in the process of being installed, including the cost associated with installation of new assistive listening systems. The list shall be updated annually thereafter.
f. This section shall not apply to capital projects involving the construction or reconstruction of assembly areas that are not owned by the city unless 50 percent or more of the estimated cost of such project is to be paid for out of the city treasury, provided that this exemption shall not apply to any capital project that receives $1,000,000 or more out of the city treasury.
g. The mayor may exempt from this section projects accounting for up to 20% of the capital dollars in each fiscal year subject to this section for the installation of assistive listening systems if in his or her sole judgment such exemption is necessary in the public interest. At the conclusion of each fiscal year the mayor shall report to the council the exemptions granted pursuant to this section, including the basis for such exemption.
h. The mayor or an office or agency designated by the mayor shall promulgate rules to carry out the provisions of this section.
i. Where the mayor determines, after consulting with experts in the field of hearing disabilities and assistive listening systems and advocates for people who are hard of hearing, that there is new technology with respect to an assistive listening system that makes such system significantly more effective than an induction loop system, the mayor may promulgate a rule allowing the use of such system as an alternative to an induction loop system in accordance with subdivision b.
(L.L. 2017/051, 3/21/2017, eff 1/2/2018)
*Editor's note:** L.L. 2017/051, 3/21/2017, eff. 1/1/2018, § 2 provides: "This local law takes effect on January 1, 2018, and applies to projects for which an application for construction document approval is filed with the department of buildings on and after such date, except that prior to such effective date the mayor or office or agency designated by the mayor shall take all actions necessary for the timely implementation of this local law, including the promulgation of rules."